1) Which of the following is NOT a phase in the waterfall model? a) Requirement gathering b) Design c) Risk management d) Testing 2) Which of the following is a benefit of the waterfall model? a) Adjusting scope during the life cycle can end a project b) High amounts of risk and uncertainty c) It is difficult to measure progress within stages d) Phases are processed and completed one at a time. 3) Maintenance is the final phase in waterfall model. a) True b) False 4) A stage in which individual components are integrated and ensured that they are error-free to meet customer requirements. a) Coding b) Testing c) Design d) Implementation 5) Methodology in which project management processes were step-by step. a) Incremental b) Waterfall c) Spiral d) Prototyping

Waterfall Model - Quiz