Which of the following best describes the main goal of project management?, Completing as many tasks as possible regardless of cost, Applying knowledge and skills to meet project requirements within constraints, Maximizing profits by minimizing team size, Avoiding any project risk entirely, In the Earned Value Method (EVM), a negative Schedule Variance (SV) indicates that the project is..., Ahead of schedule, Over budget, Behind schedule, On time, According to the Critical Path Method, what is the critical path?, The path with the most parallel activities, The longest duration path required to complete the project, The shortest path with the least dependencies, The path with the lowest total cost.